I have Test Plan in Jmeter having following three sections:

  1. Login (HTTP Sampler)
  2. Runtime Controller (Containing HTTP POST Requests)
  3. Logout (HTTP Sampler)

I want to schedule the test in following way:

  1. 300 users LOGIN
  2. Once all the users are logged in, the Runtime Controller runs for 1 hour posting HTTP Post request
  3. All the 300 users logout.

I have set the Thread group to 300 users, and Runtime controller duration to 3600 seconds. But I have observed that the Login, POST requests and Logout are not synchronized the way I want it to be.

I am new to Jmeter, please help!

网友答案:

You need Synchronizing Timer to achieve 300 users doing same activity concurrently.

Synchronizing timer blocks or holds the threads at a point till x no. of threads are blocked. It then releases all blocked threads at once so that peak concurrent load (300 users doing post activity at a time) is achieved.

you should follow below sequence,

Please change Number of Simulated Users to group by to 300 i.e your needed users.